Asterix · Electrical systems · Phase one

Batteries and electrics.
Power for life aboard.

New batteries, charging equipment and a clearer picture of what is happening behind the panels. The first chapter of Asterix’s electrical work, from the February inspection through the summer refit.

Phase one completePhotographic record: February–July 2026Words: Jason
23 June 2026The Victron BMV-712 Smart battery monitor mounted in the panel.

Getting to know what was already there.

At the first inspection in February, the electrical system was one of the areas that clearly needed attention. There was an established switchboard, battery monitoring and charging equipment, together with a great deal of wiring around the engine and behind the panels.

The first job was to understand it: which cables belonged to which circuit, how the batteries were connected and what the existing equipment was actually telling us. The photographs became a useful record as we opened things up.

14 February 2026The electrical installation at the first inspection, with wiring running above and beside the engine.
14 February 2026The existing switchboard and instruments at the start of the project.

The wiring we inherited.

These June photographs show the amount of cabling around the engine compartment as we worked through the existing installation.

23 June 2026Where we started: the cabling above and beside the Perkins engine.
20 June 2026Where we started: an overview of the wiring across the engine compartment.

Clearing out redundant cables.

We removed the redundant cabling shown gathered in the cockpit without any loss of functionality aboard Asterix. It was a tangible first step towards making the installation easier to understand and work on.

20 June 2026Redundant cabling removed from Asterix without any loss of functionality, gathered in the cockpit during the work.

A new starting point for stored power.

We bought four West Marine Group 31 AGM dual-purpose batteries for the house bank. At 105 amp-hours each, that gives us a nominal 420 amp-hours at 12 volts. A separate 105 amp-hour battery serves the engine.

With the new batteries aboard, the work moved to the compartment, the heavy cables and the connections around them. It is an awkward area to work in, and closely tied to the engine installation, so access and a clear record of the wiring mattered.

27 May 2026New batteries aboard, ready for the next stage of the electrical work.
15 June 2026The batteries in their compartment alongside the engine installation.

From the dock and from the engine.

The shore-power side of phase one centres on a Cristec CPS3 12-volt, 40-amp charger. Under way, the Perkins carries a Balmar 100-amp alternator with an external MC-614 regulator. The alternator is driven by the engine’s single V-belt.

Our July notes record the alternator output connected to the house-bank switch, with a Blue Sea Systems SI-ACR in the arrangement linking the house and engine banks for charging. That gave us a defined set of equipment to work through as we investigated charging and battery behaviour.

28 May 2026The Cristec CPS3 12V–40A shore-power charger.
June 2026 archiveThe Blue Sea Systems SI-ACR automatic charging relay, photographed before fitting.
July 2026 archiveIdentification on the Balmar alternator fitted to the Perkins.

Making sense of the numbers.

The old SmartGauge and SmartBank arrangement took some investigation. In June, the SmartGauge continued to show Error 04, and we compared its readings with measurements taken directly at the batteries while checking connections and grounds.

We added a Victron BMV-712 Smart battery monitor. Having a dedicated monitor was an important part of understanding what was happening to the new bank, rather than trying to judge everything from an occasional voltage reading.

The photographs capture both stages: the old error display and the new Victron instrument in place. The exact cause of the old fault is not something we can establish from the photographs alone.

17 June 2026The old SmartGauge displaying Error 04 during the June investigation.
23 June 2026The Victron BMV-712 Smart battery monitor mounted in the panel.

The less visible part of the job.

Much of the electrical work happens behind panels and beside the engine. The June and July photographs show cables and components laid out in the cockpit, the heavy battery connections and individual terminations being examined.

It is useful to keep this part of the record alongside the new equipment. Batteries and instruments are the visible purchases; understanding the wiring between them is just as much a part of bringing Asterix back together.

25 June 2026Cables and removed components laid out in the cockpit during the work.
25 June 2026Heavy battery cables and the covered terminal arrangement during the June work.
4 July 2026A closer record of the wiring and connections as the work progressed.

The completed installation.

With the redundant cables removed, the phase-one battery and electrical installation is complete. These photographs show the arrangement we now have aboard Asterix: the battery bank and main cabling beside the engine, and the cable routes above and around the engine compartment.

6 July 2026The completed phase-one installation: cable routing above and beside the engine.
6 July 2026The completed phase-one installation: the battery bank and main cabling in the engine compartment.

The arrangement recorded in July.

Part of the system Equipment aboard
House bank 4 × 105Ah West Marine Group 31 AGM dual-purpose batteries · 420Ah nominal at 12V
Engine battery Separate 105Ah battery
Shore charger Cristec CPS3 · 12V, 40A
Engine charging Balmar 100A alternator · external MC-614 regulator · single V-belt
Battery combining Blue Sea Systems SI-ACR
Battery monitoring Victron BMV-712 Smart

A foundation for the next phase.

Phase one is the batteries, charging and the work to understand the existing electrical installation. The navigation electronics and new autopilot belong to the next phase, with their own wiring and installation story still to be told.

That keeps this chapter focused on the power behind life aboard: storing it, charging the banks and being able to see what the system is doing.