Main mast restoration
Asterix · Masts and sails · Refit in Oxnard
The track is on.
At last.
From a metric-and-imperial mismatch to nine sections fitted up the main mast. A fiddly job of matching holes, securing screws and working together between deck and masthead.
Current position · 8 November 2026
Completed: replacement main-mast track fitted over 4–5 November, with the holes eased to suit the existing inserts and the fourth keysert from the top replaced and epoxied in.
Final account: all screws fitted with good fixings by the end of Thursday 5 November.
Still to prove: sail-car movement and the track in use with the new sails. The physical installation is complete; sailing tests have not yet been recorded.
01 / Where we started
Corrosion at the fixings.
A track that needed replacing.
The reason for changing the main-mast track was the condition of the old aluminium around its fixing points. It had corroded where it met the stainless-steel screws and the stainless-steel threaded inserts, or Keyserts, fitted into the mast. Material had been eaten away around those connections, leaving the track badly damaged.
These close-ups show the deterioration that prompted the replacement. The early photographs show the main mast with its original track and sail cars. That existing installation set the fixing positions we would have to work with when fitting the replacement.
Replacing the track meant more than choosing a length of extrusion. Its fixing holes had to line up with the inserts already in the mast, right through the full run to the masthead.
02 / Removing the track and painting · Trip Three
The track came off.
Then the mast could be painted.
Before fitting the replacement track in Trip Four, we had already removed the old track and repainted the main mast during Trip Three, with the painting completed around 2–3 August.
There were about 150 screws to deal with. I managed to remove them with only one breaking off, although two others refused to turn in the usual way. For those, I cut the track and used the cut sections as a spanner to turn the stubborn screws out.
With the old track removed, I went back up and sanded the whole mast with 120-grit abrasive. Another trip aloft followed to wash the mast thoroughly, removing the sanding dust and other surface contamination before painting.
We then painted the main mast in two coats: the first on one day and the second the following day. That left the mast freshly coated and ready for the replacement track, which we returned to fit during Trip Four.
03 / The first attempt · October
When 100 mm
is not four inches.
On 19 October Amanda prepared the first 2.5-metre sections on deck with rubber backing, screws and Tef-Gel. I climbed to the main masthead and hauled up the first piece, only to find that the holes did not match.
The new sections had 100 mm hole centres. The old track and existing mast fixings were at four inches—101.6 mm. A small difference at each hole accumulated along the section until installation was impossible.
We stopped, cleaned and repacked the unsuitable track, and arranged its return. The correctly spaced replacement was ordered in six-foot lengths. By the end of October the new sections and splices were aboard, and a trial fit matched the existing spacing.
That got us past the first obstacle. The full installation still had plenty more work waiting for us.
04 / Fitting the replacement · 4–5 November
About 150 screws.
Almost every hole needed attention.
When I went back to the top of the main mast, it became apparent that the holes would need individual adjustment. We decided to start from the bottom and build upwards through the nine sections—about eight and a half full lengths in total.
The first two went on fairly easily. Then the pattern became clear: dress the track hole, ease it until it lined up with the keysert in the mast, and check the screw. With roughly 150 screws along the run, that was a lot of repetition from a bosun’s chair.
I worked out a routine using the drill to ease the track holes and a 10-24 tap to clear remaining aluminium that was partly obstructing some of the threaded openings. That helped us obtain sound fixings as each section went on.
By the end of the first day we had about five sections on. Most of the screws had taken well, but a few still needed attention. The remaining upper sections proved especially awkward the following day.
Amanda on deck, Jason aloft
Amanda prepared the sections below and sent them up to me. That kept the job moving while I worked on matching the holes and securing each length. It was a steady partnership between the deck and the mast.
Near the top, I replaced the keysert at the fourth hole down and epoxied it in. Mixing and applying epoxy from a bosun’s chair is never the easiest job, although by then I had had plenty of practice from painting the mizzen.
By Thursday afternoon all the track was on and the screws had good fixings. It was a fiddly, tiring job, and a very good one to cross off the list.
05 / The working record
From removal and painting to a fitted track.
| Stage | Recorded result |
|---|---|
| Reason for replacement | Original aluminium track corroded around the stainless-steel screws and Keysert fixing points |
| Old-track removal · Trip Three | About 150 screws; one broke, two stubborn screws removed using cut track as a spanner |
| Main-mast preparation · Trip Three | Whole mast sanded with 120-grit abrasive, then thoroughly washed |
| Main-mast painting · Trip Three | Two coats on successive days, around 2–3 August · Trip Three |
| Initial replacement track | 100 mm spacing did not match the existing four-inch centres; returned |
| Replacement | Correctly spaced six-foot lengths and splices received |
| Installation | Nine sections, approximately 150 screws; holes eased individually as required |
| Thread preparation | 10-24 tap used to clear obstructed threaded openings |
| Insert repair | Fourth keysert from the top replaced and epoxied in |
| Position by 5 November | Track fitted, with good final screw fixings |
06 / What comes next
Ready for the sails.
More masthead jobs ahead.
The next check for the track itself is with the sail cars and new mainsail: movement along the complete run and, in due course, operation under sail. At the time of the week-three log, our contact in Hong Kong was still waiting to hear from the sail factory.
Separate main-mast jobs remain: an aerial cable and a power cable to the masthead, a fitting to raise the navigation light above the truck, a small block for the burgee halyard and a Windex. The existing messengers still need assessing before we pull cables.
Those jobs do not take away from this week’s milestone. The replacement track is finally fitted, and we have finished this round of long days working aloft.