Deck leaks and headlining
Asterix · Refit in Oxnard
Keeping the water out.
Renewing what’s beneath.
A leak above the chart table led us from tired headlining to the deck drains and wooden sprayhood bridge. Fix the source first; then rebuild the interior.
Current position · 31 October 2026
Deck work: redundant holes filled and the reshaped wooden bridge pieces refitted. Sealing work also carried out at the mizzen deck collar.
Interior: affected headlining removed, reusable panels being prepared and 30 yards of white marine vinyl ordered.
Still to confirm: whether the repairs keep the water out in further rain. The headlining has not yet been replaced.
01 / The starting point
The rain showed us
where to begin.
On 22 October, rain found its way into the starboard side above the chart table. The headlining was already on our refit list, but we could not put a fresh interior over an active leak.
Removing the panels exposed the deck-drain arrangement beneath the wooden sprayhood bridge. The old copper pipe and sealant were not keeping the water out. A separate leak was traced to the mizzen mast’s deck collar.
02 / Work so far
Lift it, repair it,
then put it back.
We removed the wooden bridge pieces and opened up the area for inspection. Amanda stripped away the old varnish and sealant and sanded the wood. I prepared and filled the redundant holes, including the old deck-drain holes and holes left by removed fittings.
The bridge pieces were reshaped with drainage openings, allowing water to pass beneath them towards the cockpit drains. Once prepared, they were bedded and refitted. We also cleaned and resealed the mizzen deck collar.
The dated record
Leak investigated; headlining removed and the deck-drain arrangement identified as the source.
Bridge pieces removed, stripped and reshaped; redundant holes prepared and filled. Bridge pieces refitted on 27 October.
White marine vinyl ordered. Amanda working on removing the old adhesive from the reusable plywood panels.
03 / The working record
Materials in this stage.
| Material | Use recorded in the log | Position |
|---|---|---|
| Epoxy resin and fillers | Redundant deck holes and repairs to the wooden bridge pieces | Used |
| Clear Flex Paste | Bridge bedding and mizzen deck-collar sealing | Used; rain check pending |
| Goof Off | Removing old adhesive from reusable panels | Preparation underway |
| White marine vinyl | Replacement headlining; 30 yards ordered | Awaiting arrival |
This records our work aboard Asterix. Long-term results will be added as they become known.
04 / Next steps
Check the repair.
Then renew the lining.
- Check the repaired areas in further rain and record any remaining water entry.
- Continue cleaning and preparing the reusable plywood panels.
- Receive the new vinyl and complete the headlining work once the areas are ready.
- Add photographs of the finished lining and a later report on how the repairs hold up.
The job remains open. We will update this page as the work progresses, keeping the earlier stages here for reference.